Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Brazil (SA.BR)

Planning and Scheduling Manager, CIRJ - Consórcio Integrador Rio de Janeiro - (Odebrecht/CH2M Hill Consortium), Rio2016 Infrastructure Integrator Program

START Date: 
February, 2013
END Date: 
August, 2014
- Planning manager/lead planner at Rio de Janeiro Infrastructure Integrator Program for 2016 Games monitoring around 170 projects in Primavera P6.- Responsibilities: Planning sector leader. Integration and analysis of Program information. Content integration with other sectors and quality check. Expert judgment for board and management decisions. Training and evaluation of deliveries and resources. -Achievements: Planning sector process mapping and definition. Training of all interface sectors.
Experience Hours (Planning & Scheduling): 
3000

Lead/Senior Planning Engineer, Time-Now Engenharia S/A, Horizonte 2 Project

START Date: 
September, 2015
-Senior planning engineer at Horizonte 2 Project, brownfield plant adjacent to existent pulp plant (Horizonte 1) at Três Lagoas – MS - Brazil. Monitoring, controlling and reporting of Fiberline (Andritz), Chemical Plant (AkzoNobel), Oxygen Plant (Praxair). Consolidation and revision of Program Report from 09/2015 to 04/2016.-Responsibilities: Expert Judgment on planning/scheduling questions. Integration and analysis of planning information. Analysis of the quality and reliability of information.
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
50

Senior Planning Engineer, Time-Now Engenharia S/A, Horizonte 2 Project

START Date: 
September, 2015
END Date: 
September, 2017
-Senior planning engineer at Horizonte 2 Project, brownfield plant adjacent to existent pulp plant (Horizonte 1) at Três Lagoas – MS - Brazil. Monitoring, controlling and reporting of Fiberline (Andritz), Chemical Plant (AkzoNobel), Oxygen Plant (Praxair). Consolidation and revision of Program Report from 09/2015 to 04/2016.-Responsibilities: Expert Judgment on planning/scheduling questions. Integration and analysis of planning information. Analysis of the quality and reliability of information.
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
50

Marcos Lemes

First Name: 
Marcos
Last Name: 
Lemes

Civil Engineer with experience in est

Professional Since: 
Jul-2000 (24.9 yrs experience)
Oldest experience: 
May 2011 (14.0 yrs experience, WARNING: 10.8 years variance with Professional Since)
Years Experience: 
3

Cost Engineer, CONSTREMAC Construções, BRAZIL

START Date: 
May, 2011
END Date: 
September, 2013

Cost engineer responsible for technica

Experience Hours (Planning & Scheduling): 
4500
Experience Hours (Cost Management): 
4500

Cost Engineer, OAS Engenharia, Latin America

START Date: 
October, 2013
END Date: 
January, 2015

Cost engineer responsible for technical visits to check local conditions and availability resources, quantitative surveying, bill of quantities, unit costs, physical-financial schedules and work plans for technical and commercial proposals submitted to public agencies in Latin America.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500

Cost Engineer, PRUMO LOGÍSTICA S/A, Capital Expenditure (Capex) & Opex

START Date: 
February, 2015

I'm responsible for the structuring and implementation of cost estimation process for capital projects (CAPEX) in O&G Direction. Also I plan and estimate the CAPEX studies requested by O&G Direction and Business Development in their feasibility studies and assist them to choose the best alternative for the development of business opportunities that meet the company's interests. For the Supply Management, I aid them technically in procurement and negotiation processes of engineering contracts.

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
5000

Cost Engineer, PRUMO LOGÍSTICA S/A, Capital Expenditure (Capex) & Opex

START Date: 
February, 2015

I'm responsible for the structuring an

Salesio Medeiros

First Name: 
Salesio
Last Name: 
Medeiros
Experience in Project Management / Petrochemical . Portfolio management experience , planning, monitoring and control maintenance, shutdowns and projects / works in the fields of oil and gas, chemical, petrochemical , automotive and steel industry. Strong focus on processes and Standards ( PMO) , Advanced knowledge in key software for project management ( Primavera P6 , MS -Project / Project) and ERP (SAP , Maximo ) .
Professional Since: 
Jul-2013 (11.9 yrs experience)
Oldest experience: 
Mar 2006 (19.2 yrs experience, WARNING: 7.3 years variance with Professional Since)
Years Experience: 
10

Planning Technician, MEDEIROS TERRAPLENING (47) 3425-5555 - Eng. Vanessa, Msproject

START Date: 
March, 2006
END Date: 
October, 2006

Planning and Control of the activities of the area of construction and metal structure, MsProject System, CDASUL Petrobras in Itajaí / SC - Fiscal - (47) 3420-4225 - Alessandra

Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2400
Experience Hours (Forensic Analysis): 
2400