Strutting
Strutting
To install simple horizontal heavy duty strutting, a typical rate of 2 days per strut/gang is reasonable.
To install diagonal slab/roof cross-brace strutting, a typical rate of 6 days per strut/gang is reasonable.
To remove these struts, allow a rate of 3.5 days per strut.