Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Road Surfaces

Barber Greene 8798 machine laying 100 mm in two coats (m2/hr)...

  • Tarmacadam = 160.0
  • Asphalt = 145.0

Manual laying 100 mm in two coats (m2/hr)...

  • Tarmacadam = 7.7
  • Asphalt = 5.0
  • Average laying of Asphalt wearing Course=40 Ton/hr so one crew can do 400 ton of asphalt /day

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.