Planning Engineer, Interbuild Engenharia e Construções, Assai Menino Marcelo

START Date: 
October, 2012
END Date: 
February, 2013

- Planning engineer at wholesale superstore construction Project - Pão de Açúcar Group - Atacado Assaí – Maceió – Alagoas – Brazil. Deadline for partial delivery of works - 80 days. Deadline for the conclusion of works - 110 days. Responsible for physical and financial planning and control. Contractors and suppliers management. Critical supply analysis. General contract management support.

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
150