Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Retained Logic

A method of calculating the Critical Path in partially completed projects taking account of Out of Sequence Progress.

Where activities have been progressed out of sequence, Predecessor Activities are reduced to their Remaining Duration and predecessor dependencies are maintained.

See Progress Over-Ride.

Market Place

No results found... (try selecting a different content filter)