A method of calculating the [[Critical Path]] in partially completed projects taking account of Out of Sequence Progress.
Where activities have been progressed out of sequence, Predecessor Activities are reduced to their [[Remaining Duration]] and predecessor dependencies are maintained.
See [[Progress Over-Ride]].