OFC Laying
OFC Laying
By Using Concrete/Road Cutter Equipment
Resources
- Survey Team of 4 (1 Suveyor , 3 Assistants)
- Equipment with Operator and Helper
- Cutting Line Marking team ( 2-3 Persons)
- OFC cable laying team ( 4 Persons)
- Splicing team (2 technicians )
Productivity
if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be achieved.
By using trenching machine
- Equipment with Operator and helper
- Mini Dozer with operator
- OFC Laying laying team (6-8 persons)
- Rest resources as per above
Productivity
If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.