Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

OFC Laying

OFC Laying

By Using Concrete/Road Cutter Equipment

Resources

  • Survey Team of 4  (1 Suveyor , 3 Assistants)
  • Equipment with Operator and Helper
  • Cutting Line Marking team ( 2-3 Persons)
  • OFC cable laying team ( 4 Persons)
  • Splicing team (2  technicians )

Productivity

if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be  achieved.

By using trenching machine

  • Equipment with Operator and helper
  • Mini Dozer with operator
  • OFC Laying laying team (6-8 persons)
  • Rest resources as per above

Productivity

If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.

Market Place

No results found... (try selecting a different content filter)