Road Basecourse
A good rule of thumb for the construction of road basecourse
Urban environment:
- Spread & Compact Production = 30m3/hr
- Trimming Production = 250m2/hr
Rural environment:
- Spread & Compact Production = 50m3/hr
- Trimming Production = 350m2/hr