Waffle Flooring

Rate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr). Conservative Erection Rate...

  • 2.4 m grid, ne 3.5 m high soffit = 1.42 m2/hr
  • 3.5 - 5.5 m high soffit = 1.13 m2.hr

Typical composite rate of 18.5 m2/day per 4 man gang. Rate includes decking, waffles and reinforcement fixing.

 