Dewatering
To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...
- Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and running.
- A larger system, with 10 - 15 holes, for a station type cofferdam will take in the region of 3 weeks with 2 rigs. This can be speeded up with the use of more rigs to reduce the well boring times.
A typical rate of 2.5 days per pump installation can be used to calculate detailed pumping arrangements. The water level can be dropped in a "closed cofferdam" within a 6 to 8 hour period for a 25,000 m2 cofferdam with a 2 m water level reduction. For smaller closed areas it will take only a few hours at most to reduce the water level by 2.5 - 3 metres.
Recharge System - Average well depth of say 55 m deep, not into rock, 9 wells in 10 days or 1.11 days/no with an additional 4 - 5 days to connect pipework and recharge backup tanks etc.
Dewatering
Task / Description | Slow | Ave | Fast | Units |
Setup small 2 hole system | 10.0 | 8.0 | 6.0 | days |
Setup large 15 hole system | - | 21.0 | - | days |
Calculate system times per pump | - | 2.5 | - | days/pump |
Setup Recharge System | - | 3.5 | - | days/pump |