Excavate and Remove

 

Excavate and Remove
Task / DescriptionSlow  Ave  Fast   Units
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk12.3 18.5 23.2  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay11.2 16.9 21.3  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil25.4 30.3 35.7  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds25.6 31.3 37.0  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk22.5 27.8 33.3  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay18.9 24.4 30.3  m3/hr
 Load Spoil to Barge, capacity 2,000m3-  8.0 -   hrs
 Load Spoil to Barge, capacity 1,500m3-  6.5 -   hrs
 Load Spoil to Barge, capacity 1,000m3-  5.5 -   hrs
 Spoil conveyor, 600mm belt, 150m/min-  260.0 -   m3/hr
 