Reinforcement Ratios

Reinforcement Ratios

Task / DescriptionSlow  Ave  Fast   Units
 Pile Cap, Concrete m3 x Ratio = Rebar Tonnes-  14.8 -   % ratio
 Base Slab, Concrete m3 x Ratio = Rebar Tonnes-  13.2 14.1  % ratio
 Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes-  20.6 25.6  % ratio
 Platform Slab, Concrete m3 x Ratio = Rebar Tonnes-  15.6 -   % ratio
 Columns, Concrete m3 x Ratio = Rebar Tonnes15.8 18.7 28.7  % ratio
 Walls, Concrete m3 x Ratio = Rebar Tonnes14.7 15.0 -   % ratio