Concrete Finishing
Concrete Finishing
Task / Description | Slow | Ave | Fast | Units |
Surface Finishing, Steel Float By Hand | 9.2 | 13.9 | 25.0 | m2/hr |
Surface Finishing, Wood Float By Hand | 11.7 | 17.2 | 29.4 | m2/hr |
Surface Finishing, Power Float | 13.9 | 20.8 | 37.0 | m2/hr |
Surface Finishing, Light Brush on Trowel | 55.8 | 90.1 | 170.0 | m2/hr |
Surface Finishing, Brush on Trowel Margin | 28.8 | 48.5 | 85.0 | m2/hr |
Surface Finishing, Sprayed By Pump, expose aggregate | 65.0 | 95.0 | 145.0 | m2/hr |
Surface Finishing, Wire Brush, expose aggregate | 15.0 | 25.0 | 30.0 | m2/hr |
Making Good Walls, prepare, shutter, pour | - | 5.5 | 8.6 | m2/hr |
Making Good Columns, prepare, shutter, pour | - | 2.8 | 6.9 | m2/hr |
Making Good Sides of Beams, prepare, shutter, pour | - | 2.8 | 7.0 | m2/hr |
Making Good Slab Soffits, prepare, shutter, pour | - | 4.2 | 5.5 | m2/hr |
Making Good Bolt Holes, prepare, shutter, pour | 14.8 | 16.8 | 25.8 | no/hr |
Making Good Rubdown Precast Concrete, prepare, shutter, pour | - | 18.0 | - | m2/hr |
Making Good Scabble 3 head brush hammer, prepare, shutter, pour | 30.7 | 59.5 | 73.8 | hrs/m2 |