Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Cable Car

The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:

  • 5 months lead time to the mast foundation contract before the cable car contractor can get access to the foundation for a 10 months installation works. 
  • The cable car contractor's installation is followed by the last 2 months of their overall 6 months testing and commissioning. 
  • This is then followed by a 4 months of Test & Trial Running. 

The 27 months programme of cable car's manufacturing, delivery, installation and test and commissioning is based on the extract of the supplier's programme.

Market Place

No results found... (try selecting a different content filter)