Rule of Thumb
Rule of Thumb
Task / Description | Slow | Ave | Fast | Units |
Site Investigation Pre Drilling | 5.0 | 4.0 | 3.0 | days/no |
Ground Excavation, Hydraulic Backhoe | - | 50.0 | - | m3/day |
Bored Piling, 25-70m deep | 10.0 | 8.0 | 6.0 | days/no |
Formwork Fixing | - | 12.0 | - | m2/day |
Reinforcement Fixing | - | 0.7 | - | Tonnes/day |
Concrete Placement | - | 16.0 | - | m3/day |
Scaffold Erection, Steel Falsework | - | 140.0 | - | m3/day |
Blockwork Laying | - | 7.0 | - | m2/day |
Plastering and Rendering | - | 12.0 | - | m2/day |
Blockwork Laying | 7.0 | 12.0 | 17.5 | m2/day |
Stonework Cladding | - | 5.1 | - | m2/day |
Window Glazing | - | 1.5 | - | m2/hr |
Granolithic Flooring | - | 4.5 | - | m2/hr |
Floor Screeding | - | 4.5 | - | m2/hr |
Floor Screeding | - | 60.0 | - | m2/day |
Ceramic Wall Tiling | - | 1.5 | - | m2/hr |