Task / Description | Slow | Ave | Fast | Units |
Site Hoarding, timber posts, plywood nailed to horizontal rails | 1.0 | 1.2 | - | m/hr |
Post Erection, Timber / Metal, dig, erect, fix | 3.3 | 4.5 | - | no/hr |
Post Erection, Concrete, dig, erect, fix | 3.2 | 4.0 | - | no/hr |
Fence Erection, Chainlink, posts at 1.5m | - | 4.2 | - | m/hr |
Fence Erection, Chainlink, posts at 2.0m | - | 4.4 | - | m/hr |
Fence Erection, Chainlink, posts at 3.0m | - | 5.5 | - | m/hr |
Fence Erection, Chestnut Pailings, posts at 1.5m | - | 23.8 | - | m/hr |
Fence Erection, Chestnut Pailings, posts at 2.0m | - | 33.3 | - | m/hr |
Fence Erection, Chestnut Pailings, posts at 3.0m | - | 41.6 | - | m/hr |
Fence Erection, Barbed Wire, posts at 1.5m | - | 71.4 | - | m/hr |
Fence Erection, Barbed Wire, posts at 2.0m | - | 100.0 | - | m/hr |
Fence Erection, Barbed Wire, posts at 3.0m | - | 125.0 | - | m/hr |
Gate Erection, Chainlink on frame | - | 4.1 | - | no/hr |