Ramp formwork
Activity | TASKS | Task - UOM | Labor (L) - Carpenter (Mandays) | Labor (L) - Helper (Mandays) | Material (M) | Material (M) | Material (M) |
Ramp formwork | Ramp - Shuttering & Providing Support | Sqm | 0.22 Mandays/Sqm | 0.44 Mandays/Sqm | MS Floor Form Panel - 750 x 600 - 13.3Nos/10Sqm | MS Floor Form Panel - 1250 x 500 : 6.4Nos/10Sqm | Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm and Shuttering Oil : 5Ltr/10Sqm |
Ramp - Deshuttering & Stacking Appropriately at Same Location | Sqm | 0.13 Mandays/Sqm | 0.26 Mandays/Sqm |