Start-to-Finish

A relationship between two activities where the [[Successor]] activity (the second activity) cannot finish until the [[Predecessor]] activity (the first activity) has started.

This is essentially an illogical [[Dependency]] as it implies time running backwards, however, it is sometimes used to schedule the successor activity 'as late as possible' in relation to the predecessor activity.