Lift Installation
Lift Installation
Sequence of Work
A standard installation sequence for a "conventional hydraulic lift with 2 - 3 storeys and doors etc.
- Handover of lift shaft structure and associated lift machine room.
- Deliver all materials to site, 2 weeks.
- Hoisting of machine roof equipment, setting out and plumbing, pit channel, car brackets and guide rails, 10 days.
- Hoist in hydraulic arm, piping, lift shaft trunking and conduits etc and wiring of lift shaft, 9 days.
- Positioning of motor control room equipment, machine room trunking and conduits and machine room wiring etc, 13 days.
- Install sill angles and architraves etc, landing grouting done by others and landing doors, 9 days.
- Partially dismantle lift shaft scaffolding and install pit equipment, 5 days.
- Install car frame and platform, car wall panels and ceiling, car door operators and wiring of lift car, 14 days.
- Architectural finishing stop work period, to install external glazing (if any) complete landing finishes and lift shaft final BS lighting, detectors etc, 12 days.
- Lift machine room Power‑On required.
- Initial tuning and adjustments, 7 days.
- Final tuning and adjustments, 7 days.
- Submission of Form 5 to EMSD.
- Interface testing with other contractors, carried out at later state (coordinated with others), duration of 6 days.
- Final test and commissioning with client and handover, 2 days.
Procurement
- Lifts are long lead items - from 12 weeks for a standard lift and considerably longer (1 to 1.5 years) for specially designed installations
Installation Periods
Therefore, the overall duration of the installation, including delivery, architectural finishes, by others, and Form 5 submission etc...
Rule Of Thumb
Upto 8 storeys = 12 - 16 weeks
Upto 15 storeys = 16 - 24 weeks
More Accurately
2 to 3 storey installation = 3 wks/level
4 storeys and above = 2 wks/level
Test & Commissioning
Rule of thumb, allow 2 weeks plus 1 day per lift per storey.
Lift Installation
Task / Description | Slow | Ave | Fast | Units |
Hydraulic Lift, Install 2 to 3 storeys | - | 3.0 | - | wks/floor |
Hydraulic Lift, Install 4 storeys and above | - | 2.0 | - | wks/floor |
Hydraulic Lift, Testing allow 2 wks plus | - | 1.0 | - | day/floor |
Standard Lift, Manufacture, test and deliver | - | 12.0 | - | wks |
Non-Standard Lift, Manufacture, test and deliver | 75.0 | 65.0 | 52.0 | wks |
Comments
Lift Installation Primaver P6 XER
https://bibloteka.com/product/lift-installation-time-schedule-in-primave...