Partitioning
Partitioning
Task / Description | Slow | Ave | Fast | Units |
Timber Studding | 5.9 | 6.2 | 6.8 | m/hr |
Metalwork System (MF) Studding | 1.6 | 2.0 | 2.5 | m2/hr |
Tape, Joint Sand and Top Coat Plasterboard | 1.1 | 1.5 | 2.1 | m2/hr |
Skimming to Plasterboards | 5.5 | 6.1 | 6.7 | m2/hr |
5mm Hardboard Paneling, excluding studding time | - | 3.2 | 3.6 | m2/hr |
100mm Pine Paneling, excluding studding time | 0.8 | 1.1 | 1.4 | m2/hr |
Quality Hardwood Paneling, excluding studding time | 0.3 | 0.5 | 0.6 | m2/hr |
Fix 50mm Rocksil Insulation to cavities | - | 17.8 | 20.2 | m2/hr |
Fix Timber Studding and Paramount Partitions | 2.6 | 3.0 | 3.4 | m2/hr |
Fix Timber Studding and Demountable Partitions | 0.8 | 1.1 | 1.6 | m2/hr |
Fix Timber Studding and Hills Duraboard Partitions | 3.0 | 3.5 | 3.9 | m2/hr |
Fix Timber Studding and Gyproc Laminated Partitions | 2.2 | 2.6 | 2.9 | m2/hr |
Stud Partitions, Butt Jointed, nailed | 5.9 | 7.3 | 9.1 | m/hr |
Stud Partitions, Butt Jointed, screwed | 3.5 | 4.6 | 5.8 | m/hr |
Stud Partitions, T&G Jointed, nailed | 2.9 | 3.6 | 4.8 | m/hr |
Stud Partitions, T&G Jointed, screwed | 2.1 | 2.8 | 3.7 | m/hr |
Stud Partitions, Fix Sole Plates | - | 11.1 | - | m/hr |
Stud Partitions, Fix Noggins | - | 16.6 | - | m/hr |
Stud Partitions, Drill 25-40mm Holes | - | 28.5 | - | no/hr |
Fix Toilet Partition System, Separation panels | - | 0.8 | - | hrs/no |
Fix Toilet Partition System, Wall Front Panels | - | 0.7 | - | hrs/no |
Fix Toilet Partition System, Separation Front Panels | - | 0.6 | - | hrs/no |
Fix Toilet Partition System, End Front Panels | - | 0.6 | - | hrs/no |
Fix Toilet Partition System, Hang Door to Panel | - | 0.4 | - | hrs/no |
Fix Toilet Partition System, Hand Door plugged to wall | - | 0.6 | - | hrs/no |
Fix Toilet Partition System, Fix Head Rails | - | 0.1 | - | hrs/no |