Barrette Piles
| Task / Description | Slow | Ave | Fast | Units | 
| Rule of Thumb, overall rate by Mill | 0.5 | 1.1 | 1.2 | hrs/no | 
| Fabricate reinforcement cages | - | 4.0 | - | hrs/cage | 
| Concreting barrette panels | 40.0 | 50.0 | 55.0 | m3/hr | 
| Trimming top of barrette panels | - | 2.4 | - | days/no | 
| Concrete Testing, Coring Test | 4.0 | 3.5 | 2.0 | days/no | 
| Concrete Testing, Sonic Logging Test | - | 0.7 | - | days/no |