The difference between planned and actual performance of an activity or a sequence of activities. Usually relating to differences between [[Planned Progress]], [[Planned Start]] or [[Planned Finish]] and [[Actual Progress]], [[Actual Start]] or [[Actual Finish]] but can also be applied to other project or programme parameters such as costs or budgets.
See also [[Slippage]].