Activity

TASKS

Task - UOM

L - Barbender/Fitter (Mandays)

L - Helper (Mandays)

M

M

M

Footing Reinforcement

Foot Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel

Mt

0.28 Mandays/0.1Mt

0.38 Mandays/0.1Mt

Bars - Include 5% Wastage

Binding Wire : 5 kg/0.1Mt

Cover Blocks - 10No/0.1Mt

 

Foot Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel

Mt

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars - Include 5% Wastage

  
 

Foot Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel

Mt

0.29 Mandays/0.1Mt

0.32 Mandays/0.1Mt

Bars - Include 5% Wastage

  