Copper Roofing

Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc.

Copper Roofing 

Flat Roof Copper Work = 3.0 m2/day     

Sloping Roof Copper Work = 2.7 m2/day

 