Lead Roofing

Metal roof works are usually carried out with 2 men gangs of skilled labour.

The rates do not include for the timber backing structures etc.

Lead Roofing Flat Roof Lead Work = 2.5 m2/day

Sloping Roof Lead Work = 2.1 m2/day