Installation
For windows that are not 'built-in' as work proceeds...
- Install & Fix - By Area = 2.0 m2/hr
- Install & Fix - By Girth = 4.0 m/hr
Mastic Pointing = 6.0 m/hr
Doors and Windows
| Task / Description | Slow | Ave | Fast | Units | 
| Mastic Pointing to Frames | - | 9.5 | - | m/hr | 
| Fix Metal and Timber Windows After Wall Complete | - | 2.0 | - | m2/hr | 
| Window Glazing | - | 1.3 | - | m2/hr | 
| Window Glazing, Single Glazed Units | - | 2.0 | - | m2/hr | 
| Window Glazing, Double Glazed Units | - | 1.3 | - | m2/hr |