Titanium Roofing System
Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc.
Titanium roof on multiple sub‑layers.
Typical composite rate of 9.5 m2/day.
Installation
Typical timing and sequence of works. This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)...
| Element | Week | Manpower | 
| Temporary Works | 0 - 2 | 5 | 
| Metal Decking | 2 - 3 | 12 | 
| Gutter Subframe | 3 - 6 | 6 | 
| Vapour Barrier | 4 - 13 | 4 | 
| Rockwool | 4 – 13 | 44 | 
| Cement Board | 4 – 13 | 6 | 
| Ice / Water Shield | 4 – 13 | 4 | 
| Gutter Lining | 6 - 9 | 4 | 
| Aluminium Cladding / Subframe | 6 – 11 | 6 | 
| Titanium Cladding | 8 – 17 | 17 | 
| Aluminium Pannelling | 9 - 14 | 6 |