Programme Narrative
CONSTRUCTION PROGRAMME ANALYSIS REPORT<?xml:namespace prefix = o />
Table of Contents
Introduction
- Preliminary Construction Programme
- Programme Organization
Coding and Structure
- Activity Organization Codes
- Contract Obligations
Narrative Statement
- Working Hours
- Calendar
- Constraints
- Critical Path
- Critical Path Analysis
- Filters and Layouts
- Programme Logic
- Cycle Time Analysis
- Site Layout and Site Crainage
- Designated Contractors Joint Site Inspection
- Designated Contractors / Interfacing Contractors Site Details
- Zone / Area Definitions
- Programme Sequence Sketches
- Installation Areas and Delivery Definitions
- Degree of Completion Definitions
- Trackwork Interfaces / Restraints
- Power On Dates and Equipment Energisation
- DC Traction Power On and Overhead Line Energisation
- Test Running Period
- Trial Running Period
Activity Resources and Production Rates
- Assigned Activity Resources
- Activity Resources
- Activity Production and Installation Rates
- Principle Manpower and Resource Quantities
Table of Appendices
- Coding and Structure
- Completion Obligation and Milestone Breakdown
- Activity Identification Codes
- Typical Logic Flow diagrams
- Resource Loading “S” curves
- Cycle Time Analysis
- Site Layout and Crainage
- Zone Area Layout
- Programme Sequence Sketches
- Zone Area Room Schedule
- Resource Loading Report