Externally

One coat primer, 2 undercoats, 1 gloss 1.70 m2/hr

As above to steel stanchions and beams 0.90 m2/hr

As above to balustrades, railings etc 1.00 m2/hr

As above to gutter and downpipes etc 2.50 m/hr