Planning Engineer, Dongfang Eletrical Corporation, 425 mw CCCP Power Plant in Pakinstan
START Date:
September, 2008
END Date:
January, 2010 # Power Plant CCCP AT Pakistan#33 million dollar# Develop the MPR (Monthly Progress Report)
Develop the Master Schedule and Construction Program &CPM (including engineering procurement & construction) using Primavera 6.2
Review the schedule which is submitted by construction subcontractor (according to the milestone stipulated in contract)
Establish the Project Progress Measurement System (base on p3e/c and MS Excel )
Determine the monthly actual percentage, and develop a series of progress curves such as overall progress, engineering progress, procurement progress and construction progress.