Planning Engineer, Dongfang Eletrical Corporation, 425 mw CCCP Power Plant in Pakinstan

START Date: 
September, 2008
END Date: 
January, 2010

# Power Plant CCCP AT Pakistan#33 million dollar# Develop the MPR (Monthly Progress Report)

Develop the Master Schedule and Construction Program &CPM (including engineering procurement & construction) using Primavera 6.2

Review the schedule which is submitted by construction subcontractor (according to the milestone stipulated in contract)

Establish the Project Progress Measurement System (base on p3e/c and MS Excel )