Project Planner, Fabricom Contracting Ltd, ICHP Auxiliary Boiler Installation

START Date: 
January, 2002
END Date: 
May, 2003

ICHP Auxiliary Boiler Installation with associated ductwork, steelwork and pipe work.

  •  Develop installation programme for ductwork, steelwork access and pipe work for two Auxiliary Boilers for client Foster Wheeler.
  • Project Engineer pipe work erection packs, pipe support requirements and progress tracking documentation.

Saturate Gas Plant £8 million rebuild, managed by Fluor Limited for Conoco Limited’s Humber Oil Refinery.

  • Using Primavera P3 to develop contractual fabrication and erection programs, liaising with project management team from Fluor Limited and sub-contract companies.
  • Develop acceleration programs for the dressing of three columns due to vendor 4-week delivery slippage while getting commercial and timing agreements from client.
  • Develop progress documentation, provide comprehensive weekly reports and undertake general project engineering duties as and when required.
  • Assist other business unit managers to prepare level 3 project programs for tender packs.