ICHP Auxiliary Boiler Installation

Project Planner, Fabricom Contracting Ltd, ICHP Auxiliary Boiler Installation

START Date: 
January, 2002
END Date: 
May, 2003

ICHP Auxiliary Boiler Installation with associated ductwork, steelwork and pipe work.

  •  Develop installation programme for ductwork, steelwork access and pipe work for two Auxiliary Boilers for client Foster Wheeler.
  • Project Engineer pipe work erection packs, pipe support requirements and progress tracking documentation.

Saturate Gas Plant £8 million rebuild, managed by Fluor Limited for Conoco Limited’s Humber Oil Refinery.