You're right with the calendars, sub contract activities are a 5 day week and all of our succeeding activities were on 6 days ... thanks very much for your help!
Member for
24 years 8 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Wed, 2013-05-08 14:27
I think you better post the xer file so everybody can see what's going on inside your program. Just saying. It might help better understand your problem. I never meet such problem before. But let's wait these P6 masters arround will suggest.
Member for
12 years 5 monthsYou're right with the
You're right with the calendars, sub contract activities are a 5 day week and all of our succeeding activities were on 6 days ... thanks very much for your help!
Member for
24 years 8 monthsAbble,It may happen if
Abble,
It may happen if succeding activities have different calendar (like 6 days work week instead of five).
Member for
12 years 9 monthsI think you better post the
I think you better post the xer file so everybody can see what's going on inside your program. Just saying. It might help better understand your problem. I never meet such problem before. But let's wait these P6 masters arround will suggest.