How we calculate VOWD if we have diffrent milestone weightings?

2 replies [Last post]
Jenny Ingco
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All Planners,

I am working on p6 and I just need to know How we can calculate the VOWD if we given the milestone weightings will be different from the physical progress weightings?

 

Thank you for any help...

 

Thank you,

Replies

Jenny Ingco
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Sir,

Thank you very much for your replay. I was wondering how it's possible to fit in my EPC project, if I need to monitor %progress for overall and each EPC phase using multi weight crieteria ( manhours , money, physical progress) at different phases? I use sure trak.

Hope you come forward to help me in this issue with my great thanks.

 

Hanson

Raymund de Laza
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hanson,

Can you make it clear for me if that term "Milestone" as you mentioned is the the same as the Baseline program.

I understand that milestones can never be loaded with resources.

Please Clarify.

 

Regards,