Displaying different cost rates columns in Ghantt view

1 reply [Last post]
Cheryl Biden
User offline. Last seen 13 years 4 weeks ago. Offline
Joined: 21 Feb 2006
Posts: 3

May be dead easy fix but I can't seem to find the relevant columns for displaying different totals of work based upon different rates / cost types.

I need to show effectively the values by WBS on the plan at say internal cost, selling cost etc. I have applied the rates at resources level but now need to be able to show this on the plan, help appreciated. Many thanks for looking / assisting.

Replies

Raymund de Laza
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

In my understanding, create UDF for each cost you want to show.. internal cost, selling cost, etc...with cost data type... likewise create also rate type as internal rate, selling rate, etc...

Use the Global change to change the rate type then once done use global change to copy the current budget total cost to the UDF corresponding to the rate type name. Do the same for every rate type you have.

Then you can display all the UDF columns at a time with the different cost.

 

Hope this will help.

 

Regards,