Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

why the percent complete changes after scheduling

1 reply [Last post]
Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear All,

After I enter the percentage complete for all activities and schedule,The percentage complete changes from what I have Entered.Also there are decimals seen in it.

Why its happening in P6.Do I have to change any settings.


With Thanks & Regards,

Anbin Ponnith

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Anbin

Have a look at the %-complete type:
- Physical: entered manually
- Duration or Units: calculated based on actual and remaining duration or units

Switch off "Auto Compute Actuals"

Regards

Dieter