Oracle Primavera - PM6 Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Sun, 2009-08-23 12:31 Permalink RE: why the percent complete changes after scheduling Anbin Have a look at the %-complete type: - Physical: entered manually - Duration or Units: calculated based on actual and remaining duration or units Switch off "Auto Compute Actuals" Regards Dieter Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Sun, 2009-08-23 12:31 Permalink RE: why the percent complete changes after scheduling Anbin Have a look at the %-complete type: - Physical: entered manually - Duration or Units: calculated based on actual and remaining duration or units Switch off "Auto Compute Actuals" Regards Dieter
Member for
18 years 9 monthsRE: why the percent complete changes after scheduling
Anbin
Have a look at the %-complete type:
- Physical: entered manually
- Duration or Units: calculated based on actual and remaining duration or units
Switch off "Auto Compute Actuals"
Regards
Dieter