As explained by Antonio you have to Select one project form projects directory & press (Ctrl) then select the other project then press right click & select open project, now both projects are opened concurrently.
Regards,
Hatem
Member for
16 years 9 months
Member for16 years9 months
Submitted by António Faria on Tue, 2009-01-20 06:08
Thanks for your replay, what did you mean by open both projects concurrently
here is my steps,
Projects ------ Project 1 ------ open ------ select activities ------ copy ------ projects ------ project 2 ------ open/activities view ------ past tap not active!!!!! Because when I open project 2 project 1 appeared closed.
The two projects aren’t open at same time I wander why and how can I solve this problem?
regards,
Abeer
Member for
16 years 9 months
Member for16 years9 months
Submitted by António Faria on Tue, 2009-01-20 05:42
If you create a blank project, dont forget to create a WBS structure. If not, when you are in the "Activities Workspace" and if the layout filter has a WBS filter, you will not see the new project to past in.
BR,
AF
Member for
20 years 11 months
Member for21 years
Submitted by Hatem Mahmoud on Tue, 2009-01-20 05:36
Member for
17 years 3 monthsRE: P6, Copy activities
Thanks a lot for your concern (Hatem & António).
It worked.
António because of your advice my day became happy
Regards
Abeer
Member for
20 years 11 monthsRE: P6, Copy activities
Hi Abeer,
As explained by Antonio you have to Select one project form projects directory & press (Ctrl) then select the other project then press right click & select open project, now both projects are opened concurrently.
Regards,
Hatem
Member for
16 years 9 monthsRE: P6, Copy activities
Select both projects in "Project Workspace". After they are blue (selected), you can do one of these:
1. mouse right click, select Open.
2. Menu File/Open
3. Ctrl-O
BR,
AF
Member for
17 years 3 monthsRE: P6, Copy activities
Hi Hatem,
Thanks for your replay, what did you mean by open both projects concurrently
here is my steps,
Projects ------ Project 1 ------ open ------ select activities ------ copy ------ projects ------ project 2 ------ open/activities view ------ past tap not active!!!!! Because when I open project 2 project 1 appeared closed.
The two projects aren’t open at same time I wander why and how can I solve this problem?
regards,
Abeer
Member for
16 years 9 monthsRE: P6, Copy activities
If you create a blank project, dont forget to create a WBS structure. If not, when you are in the "Activities Workspace" and if the layout filter has a WBS filter, you will not see the new project to past in.
BR,
AF
Member for
20 years 11 monthsRE: P6, Copy activities
Hi Abeer,
You have to open both projects concurrently then you can copy from one to another.
in terms of steps:
1. Open both projects from the project directory concurrently
2. Go to activities view & you will find Both projects appear as two WBS.
3. Start copying from one to another.
Hope it helps.
Regards,
Hatem