P6, Copy activities

6 replies [Last post]
Abeer Mahmoud
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear All,

At P6; How can I copy activities from project and past them at another one?


Please advise in steps.

Regards,
Abeer

Replies

Abeer Mahmoud
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Thanks a lot for your concern (Hatem & António).

It worked.

António because of your advice my day became happy


Regards
Abeer
Hatem Mahmoud
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 1 Nov 2004
Posts: 13
Hi Abeer,

As explained by Antonio you have to Select one project form projects directory & press (Ctrl) then select the other project then press right click & select open project, now both projects are opened concurrently.

Regards,
Hatem
António Faria
User offline. Last seen 9 years 16 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 40
Groups: None
Select both projects in "Project Workspace". After they are blue (selected), you can do one of these:
1. mouse right click, select Open.
2. Menu File/Open
3. Ctrl-O

BR,
AF
Abeer Mahmoud
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87

Hi Hatem,
Thanks for your replay, what did you mean by open both projects concurrently
here is my steps,
Projects ------ Project 1 ------ open ------ select activities ------ copy ------ projects ------ project 2 ------ open/activities view ------ past tap not active!!!!! Because when I open project 2 project 1 appeared closed.
The two projects aren’t open at same time I wander why and how can I solve this problem?

regards,
Abeer
António Faria
User offline. Last seen 9 years 16 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 40
Groups: None
If you create a blank project, don’t forget to create a WBS structure. If not, when you are in the "Activities Workspace" and if the layout filter has a WBS filter, you will not see the new project to past in.

BR,
AF
Hatem Mahmoud
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 1 Nov 2004
Posts: 13
Hi Abeer,

You have to open both projects concurrently then you can copy from one to another.
in terms of steps:
1. Open both projects from the project directory concurrently
2. Go to activities view & you will find Both projects appear as two WBS.
3. Start copying from one to another.

Hope it helps.

Regards,

Hatem