Problem copying a project

A
Andrew Podolny 👤 Member for 21 years 8 months

Hi Andrew.

If I’ve got you right - you are saving baseline prior to progress update. I know that P5 doesn’t preserve the Planned Star/Finish for "in progress" activities after baselining. The workaround is simple - don’t forget to run global change prior to copying the baseline:



IF Activity Status=In progress

THEN Planned Start = Start

AND Planned Finish = Finish



Hope this will help you.

Best Regards,

Andrew






Featured Partner

Top Posters

Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts

Our Partners