Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Storing Period Performances

1 reply [Last post]
stephen milburn
User offline. Last seen 7 years 38 weeks ago. Offline
Joined: 9 Feb 2006
Posts: 8
Groups: None
Hi Planners,
Would any of the experienced planners who work with P3e have some useful info including some screen shots of using storing period performance ? I am wanting to generate a useful report on this period performance and would appreciate some guidance.
e mail stephen.milburn1@ntlworld.com

Replies

Alex Wong
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Storing Period Performance and Apply Actual and Schedule need to work together, in order to give you a accurate picture of performance.

What you need to do is (assume this is your first update)

Update your data date
Schedule
Update actual start, finish, % actual cost, Actual units, remaining duration and expected finish date
Apply actuals
Schedule
Store Period Performance

Repeat this cycle each month

Good Luck