Oracle Primavera - PM6 Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2007-01-22 01:10 Permalink RE: Actual Financial period Cost disapear after copying a Filippo Sereval things you can check, 1. At the resource assignment level the period data in Sept-Oct-Nov still exist. 2. Have you summerised the schedule - if not then you will not see the updated info in tracking view 3. in the resource profile view are you display "All Project" or "Opened Project only" HTH alex Log in or register to post comments
Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2007-01-22 01:10 Permalink RE: Actual Financial period Cost disapear after copying a Filippo Sereval things you can check, 1. At the resource assignment level the period data in Sept-Oct-Nov still exist. 2. Have you summerised the schedule - if not then you will not see the updated info in tracking view 3. in the resource profile view are you display "All Project" or "Opened Project only" HTH alex
Member for
22 years 8 monthsRE: Actual Financial period Cost disapear after copying a
Filippo
Sereval things you can check,
1. At the resource assignment level the period data in Sept-Oct-Nov still exist.
2. Have you summerised the schedule - if not then you will not see the updated info in tracking view
3. in the resource profile view are you display "All Project" or "Opened Project only"
HTH
alex