Oracle Primavera - PM6 Member for 19 years 11 months Member for 20 years Submitted by Marcio Sampaio on Wed, 2006-02-08 12:13 Permalink RE: Help needed-Importing MSP to Ver.5 I understand that it is a default of Primavera - import activities as resource dependent - I never knew a place where I could configure this. I dont know if its diferent in P5, maybe some other PP member could tel us. By the way it is easy to change this using fill down. Regards. Marcio Eduardo Member for 21 years 5 months Member for 21 years 5 months Submitted by Suraj Bhatt on Wed, 2006-02-08 07:29 Permalink RE: Help needed-Importing MSP to Ver.5 Well thanks! I solved the dates problem.They match now but why did the activities became resource dependent??? Suraj Member for 19 years 11 months Member for 20 years Submitted by Marcio Sampaio on Wed, 2006-02-08 06:32 Permalink RE: Help needed-Importing MSP to Ver.5 Suraj Bhatt; Too many things can be causing this problem. Calendars, lags, relathionships, durations etc. I suggest u to check all this topics in all activities and try to find what is wrong. Good luck. Log in or register to post comments
Member for 19 years 11 months Member for 20 years Submitted by Marcio Sampaio on Wed, 2006-02-08 12:13 Permalink RE: Help needed-Importing MSP to Ver.5 I understand that it is a default of Primavera - import activities as resource dependent - I never knew a place where I could configure this. I dont know if its diferent in P5, maybe some other PP member could tel us. By the way it is easy to change this using fill down. Regards. Marcio Eduardo
Member for 21 years 5 months Member for 21 years 5 months Submitted by Suraj Bhatt on Wed, 2006-02-08 07:29 Permalink RE: Help needed-Importing MSP to Ver.5 Well thanks! I solved the dates problem.They match now but why did the activities became resource dependent??? Suraj
Member for 19 years 11 months Member for 20 years Submitted by Marcio Sampaio on Wed, 2006-02-08 06:32 Permalink RE: Help needed-Importing MSP to Ver.5 Suraj Bhatt; Too many things can be causing this problem. Calendars, lags, relathionships, durations etc. I suggest u to check all this topics in all activities and try to find what is wrong. Good luck.
Member for
19 years 11 monthsRE: Help needed-Importing MSP to Ver.5
I understand that it is a default of Primavera - import activities as resource dependent - I never knew a place where I could configure this.
I dont know if its diferent in P5, maybe some other PP member could tel us.
By the way it is easy to change this using fill down.
Regards.
Marcio Eduardo
Member for
21 years 5 monthsRE: Help needed-Importing MSP to Ver.5
Well thanks!
I solved the dates problem.They match now but why did the activities became resource dependent???
Suraj
Member for
19 years 11 monthsRE: Help needed-Importing MSP to Ver.5
Suraj Bhatt;
Too many things can be causing this problem.
Calendars, lags, relathionships, durations etc.
I suggest u to check all this topics in all activities and try to find what is wrong.
Good luck.