Loops Detected

3 replies [Last post]
Anu Tor
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Please advise me. I run data date of P3 and that one is alert " loops detected ". How is solve this problem?

Replies

Gün Göksu
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 31 Mar 2005
Posts: 123
if you use P3 v3.1 then look for the p3.out file.
open it and scroll down. you will see the loop reports.
when you clean (break/ delete a relationship inside the loop) each loop do a run (F9) again.
if still there are loops it will show under the P3.out file. you will need to do the above again.

regards
Gün Göksu
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Anu,

Loop is a circular logic within a network, if loops detected in the project, P3 cannot calculate the schedule until you eliminate all loops.

Example is when the relationship of Activity A to Activity B is SS & you link again to Activity B to A with FS then this is the loop.

To solve this problem, select the schedule icon instead of pressing F9 & tick "Schedule Now" In Output Option, mark the box next to "View on screen" tick OK & OK. Finally, check the Loop Report in Primavera Look.

HTH.

Arnold
A D
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Click on the schedule icon and it will generate a report.

In the report, You may find list of activities involved in loop. Resolve the links and its done.

:-)