Level 3 Program to Level 4 program

3 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear All,
I am having a level 3 program now some acivities in this program i want to detail into further smaller activities.For example

0784 SC Basement internal plaster
This plaster activity i want to detail for each room , now please advise
if this activity i shoud name as hammock and all smaller activities i join with ss and ff relationships.
or what would be the best presentation layout for teh said activity.
regards
deb

Replies

Pranab Kumar Deb
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=30237...

this is what i was refering to, i feel this is a very good discussion for MICRO SCHEDULING of activities.
regards
deb
Pranab Kumar Deb
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello rodel ,
thanks for the advice , i believe i will go for the WBS to detail the project further , i will take note fro your other post i saw where u mentioned the way the project should be broken down.
regards
deb
Rodel Marasigan
User offline. Last seen 17 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Deb,

Hammock is almost the same as level of effort. If you breakdown your activity to WBS, then you can define that Activity as WBS and the detail activities will be the breakdown of your WBS activity. You WBS activity then will have an automatic duration based on the earliest start and last finish date of your detail activity. You can also use hammock but you need to define the predecessor (SS relationship) of the first detail activity and successor (FF relationship) of the last detail activity.

Hope this help