Primavera Project Planner - P3 Member for 21 years Member for 21 years Submitted by David Moses on Wed, 2007-12-05 05:43 Permalink RE: Resource Calendar ? Hi There, Can we load this resource to ActID: AB100 like this: Resource Dictionary: (Using Hierarchical Resources) ManDay** (Sum of all periods) ManDayW1 (indicates winter period 1) ManDayS1 (indicates summer period 1) ManDayW2 (indicates winter period 2) ManDayS2 (indicates summer period 2) ManDayW3 (indicates winter period 3) Through Activity Detail > Resources… (Using Resource Lag and Durations) ManDayW1: [ES: Jan 08 - EF: March 08] [Res Lag/Duration: 0 Days / 90 Days] [BQ: 200] ManDayS1: [ES: Apr 08 - EF: Oct 08] [Res Lag/Duration: 90 Days /210 Days] [BQ: 600] ManDayW2: [ES: Nov 08 - EF: March 09] [Res Lag/Duration: 300 Days / 150 Days] [BQ: 200] ManDayS2: [ES: Apr 09 - EF: Oct 09] [Res Lag/Duration: 450 Days / 210 Days] [BQ: 600] ManDayW3: [ES: Nov 09 - EF: Dec 09] [Res Lag/Duration: 660 Days / 60 Days] [BQ: 200] {Assumption: Every month is 30 days} As some friends says below, how can we set the above situation by using “Resource Limits”? Any help? Regards, Member for 22 years 6 months Member for 22 years 6 months Submitted by DATTATREYA PADHARTHI on Tue, 2007-12-04 22:05 Permalink RE: Resource Calendar ? David, As Ronald has rightly pointed , use resource limits for the time period(s). Cheers datta Member for 21 years Member for 21 years Submitted by David Moses on Fri, 2007-11-30 10:46 Permalink RE: Resource Calendar ? Hi There, Assume we have an activity; ActID: AB100 ES:01.01.2008 EF:31.12.2009 Resource: ManDay But, During the summer seasons (April-October) Budgeted Quantity of Resource is 600 ManDay. During the winter seasons (November-March) Budgeted Quantity of Resource is 200 ManDay. How can I load that activity with this resource and how can I draw resource histogram for this case? Regards, Member for 21 years Member for 21 years Submitted by David Moses on Mon, 2006-10-02 05:41 Permalink RE: Resource Calendar ? Hi There, Thanks to Ronald Winter all other friends. Regards Member for 20 years 7 months Member for 20 years 7 months Submitted by Gün Göksu on Sun, 2006-09-24 02:06 Permalink RE: Resource Calendar ? hello, to be exact: go to data\resources\ select "manhour" from the menu. on the lower left limits window you can enter the periods normal/max values of said resource. please check F1 when in the window to receive related help. unfortunately there is no easy way to just say 50% less performance for said months in P3. Gün. Member for 19 years 6 months Member for 19 years 7 months Submitted by Karim Mounir on Tue, 2006-09-19 10:31 Permalink RE: Resource Calendar ? David, In the resource dictionary (Data --> Resources), select the resource u want and select limits from bottom window (select the Normal / Maximum units through the selected days). Member for 21 years Member for 21 years Submitted by David Moses on Tue, 2006-09-19 10:03 Permalink RE: Resource Calendar ? Hi there, OK.I will try. But I need some more explanations for my concern. May be I need a simple sample or I need to read some more literature for that. Regards Member for 22 years 9 months Member for 22 years 10 months Submitted by Ronald Winter on Thu, 2006-09-14 09:58 Permalink RE: Resource Calendar ? David, You are talking about Resource Leveling now. Set up your resource availbility levels per time period and then level the schedule. Good luck! Log in or register to post comments
Member for 21 years Member for 21 years Submitted by David Moses on Wed, 2007-12-05 05:43 Permalink RE: Resource Calendar ? Hi There, Can we load this resource to ActID: AB100 like this: Resource Dictionary: (Using Hierarchical Resources) ManDay** (Sum of all periods) ManDayW1 (indicates winter period 1) ManDayS1 (indicates summer period 1) ManDayW2 (indicates winter period 2) ManDayS2 (indicates summer period 2) ManDayW3 (indicates winter period 3) Through Activity Detail > Resources… (Using Resource Lag and Durations) ManDayW1: [ES: Jan 08 - EF: March 08] [Res Lag/Duration: 0 Days / 90 Days] [BQ: 200] ManDayS1: [ES: Apr 08 - EF: Oct 08] [Res Lag/Duration: 90 Days /210 Days] [BQ: 600] ManDayW2: [ES: Nov 08 - EF: March 09] [Res Lag/Duration: 300 Days / 150 Days] [BQ: 200] ManDayS2: [ES: Apr 09 - EF: Oct 09] [Res Lag/Duration: 450 Days / 210 Days] [BQ: 600] ManDayW3: [ES: Nov 09 - EF: Dec 09] [Res Lag/Duration: 660 Days / 60 Days] [BQ: 200] {Assumption: Every month is 30 days} As some friends says below, how can we set the above situation by using “Resource Limits”? Any help? Regards,
Member for 22 years 6 months Member for 22 years 6 months Submitted by DATTATREYA PADHARTHI on Tue, 2007-12-04 22:05 Permalink RE: Resource Calendar ? David, As Ronald has rightly pointed , use resource limits for the time period(s). Cheers datta
Member for 21 years Member for 21 years Submitted by David Moses on Fri, 2007-11-30 10:46 Permalink RE: Resource Calendar ? Hi There, Assume we have an activity; ActID: AB100 ES:01.01.2008 EF:31.12.2009 Resource: ManDay But, During the summer seasons (April-October) Budgeted Quantity of Resource is 600 ManDay. During the winter seasons (November-March) Budgeted Quantity of Resource is 200 ManDay. How can I load that activity with this resource and how can I draw resource histogram for this case? Regards,
Member for 21 years Member for 21 years Submitted by David Moses on Mon, 2006-10-02 05:41 Permalink RE: Resource Calendar ? Hi There, Thanks to Ronald Winter all other friends. Regards
Member for 20 years 7 months Member for 20 years 7 months Submitted by Gün Göksu on Sun, 2006-09-24 02:06 Permalink RE: Resource Calendar ? hello, to be exact: go to data\resources\ select "manhour" from the menu. on the lower left limits window you can enter the periods normal/max values of said resource. please check F1 when in the window to receive related help. unfortunately there is no easy way to just say 50% less performance for said months in P3. Gün.
Member for 19 years 6 months Member for 19 years 7 months Submitted by Karim Mounir on Tue, 2006-09-19 10:31 Permalink RE: Resource Calendar ? David, In the resource dictionary (Data --> Resources), select the resource u want and select limits from bottom window (select the Normal / Maximum units through the selected days).
Member for 21 years Member for 21 years Submitted by David Moses on Tue, 2006-09-19 10:03 Permalink RE: Resource Calendar ? Hi there, OK.I will try. But I need some more explanations for my concern. May be I need a simple sample or I need to read some more literature for that. Regards
Member for 22 years 9 months Member for 22 years 10 months Submitted by Ronald Winter on Thu, 2006-09-14 09:58 Permalink RE: Resource Calendar ? David, You are talking about Resource Leveling now. Set up your resource availbility levels per time period and then level the schedule. Good luck!
Member for
21 yearsRE: Resource Calendar ?
Hi There,
Can we load this resource to ActID: AB100 like this:
Resource Dictionary:
(Using Hierarchical Resources)
ManDay** (Sum of all periods)
ManDayW1 (indicates winter period 1)
ManDayS1 (indicates summer period 1)
ManDayW2 (indicates winter period 2)
ManDayS2 (indicates summer period 2)
ManDayW3 (indicates winter period 3)
Through Activity Detail > Resources…
(Using Resource Lag and Durations)
ManDayW1: [ES: Jan 08 - EF: March 08] [Res Lag/Duration: 0 Days / 90 Days] [BQ: 200]
ManDayS1: [ES: Apr 08 - EF: Oct 08] [Res Lag/Duration: 90 Days /210 Days] [BQ: 600]
ManDayW2: [ES: Nov 08 - EF: March 09] [Res Lag/Duration: 300 Days / 150 Days] [BQ: 200]
ManDayS2: [ES: Apr 09 - EF: Oct 09] [Res Lag/Duration: 450 Days / 210 Days] [BQ: 600]
ManDayW3: [ES: Nov 09 - EF: Dec 09] [Res Lag/Duration: 660 Days / 60 Days] [BQ: 200]
{Assumption: Every month is 30 days}
As some friends says below, how can we set the above situation by using “Resource Limits”?
Any help?
Regards,
Member for
22 years 6 monthsRE: Resource Calendar ?
David,
As Ronald has rightly pointed , use resource limits for the time period(s).
Cheers
datta
Member for
21 yearsRE: Resource Calendar ?
Hi There,
Assume we have an activity;
ActID: AB100
ES:01.01.2008
EF:31.12.2009
Resource: ManDay
But,
During the summer seasons (April-October) Budgeted Quantity of Resource is 600 ManDay.
During the winter seasons (November-March) Budgeted Quantity of Resource is 200 ManDay.
How can I load that activity with this resource and how can I draw resource histogram for this case?
Regards,
Member for
21 yearsRE: Resource Calendar ?
Hi There,
Thanks to Ronald Winter all other friends.
Regards
Member for
20 years 7 monthsRE: Resource Calendar ?
hello,
to be exact:
go to data\resources\ select "manhour" from the menu.
on the lower left limits window you can enter the periods normal/max values of said resource.
please check F1 when in the window to receive related help.
unfortunately there is no easy way to just say 50% less performance for said months in P3.
Gün.
Member for
19 years 6 monthsRE: Resource Calendar ?
David,
In the resource dictionary (Data --> Resources), select the resource u want and select limits from bottom window (select the Normal / Maximum units through the selected days).
Member for
21 yearsRE: Resource Calendar ?
Hi there,
OK.I will try.
But I need some more explanations for my concern.
May be I need a simple sample or I need to read some more literature for that.
Regards
Member for
22 years 9 monthsRE: Resource Calendar ?
David,
You are talking about Resource Leveling now. Set up your resource availbility levels per time period and then level the schedule. Good luck!