Resource Calendar ?

Member for

21 years

Hi There,



Can we load this resource to ActID: AB100 like this:



Resource Dictionary:

(Using Hierarchical Resources)



ManDay** (Sum of all periods)

ManDayW1 (indicates winter period 1)

ManDayS1 (indicates summer period 1)

ManDayW2 (indicates winter period 2)

ManDayS2 (indicates summer period 2)

ManDayW3 (indicates winter period 3)



Through Activity Detail > Resources…

(Using Resource Lag and Durations)



ManDayW1: [ES: Jan 08 - EF: March 08] [Res Lag/Duration: 0 Days / 90 Days] [BQ: 200]

ManDayS1: [ES: Apr 08 - EF: Oct 08] [Res Lag/Duration: 90 Days /210 Days] [BQ: 600]

ManDayW2: [ES: Nov 08 - EF: March 09] [Res Lag/Duration: 300 Days / 150 Days] [BQ: 200]

ManDayS2: [ES: Apr 09 - EF: Oct 09] [Res Lag/Duration: 450 Days / 210 Days] [BQ: 600]

ManDayW3: [ES: Nov 09 - EF: Dec 09] [Res Lag/Duration: 660 Days / 60 Days] [BQ: 200]



{Assumption: Every month is 30 days}



As some friends says below, how can we set the above situation by using “Resource Limits”?



Any help?



Regards,

Member for

22 years 6 months

David,

As Ronald has rightly pointed , use resource limits for the time period(s).



Cheers

datta

Member for

21 years

Hi There,



Assume we have an activity;



ActID: AB100

ES:01.01.2008

EF:31.12.2009

Resource: ManDay



But,



During the summer seasons (April-October) Budgeted Quantity of Resource is 600 ManDay.

During the winter seasons (November-March) Budgeted Quantity of Resource is 200 ManDay.



How can I load that activity with this resource and how can I draw resource histogram for this case?



Regards,


Member for

21 years

Hi There,



Thanks to Ronald Winter all other friends.



Regards

Member for

20 years 7 months



hello,



to be exact:

go to data\resources\ select "manhour" from the menu.



on the lower left limits window you can enter the periods normal/max values of said resource.



please check F1 when in the window to receive related help.



unfortunately there is no easy way to just say 50% less performance for said months in P3.



Gün.

Member for

19 years 6 months

David,



In the resource dictionary (Data --> Resources), select the resource u want and select limits from bottom window (select the Normal / Maximum units through the selected days).

Member for

21 years

Hi there,



OK.I will try.



But I need some more explanations for my concern.



May be I need a simple sample or I need to read some more literature for that.



Regards

Member for

22 years 9 months

David,



You are talking about Resource Leveling now. Set up your resource availbility levels per time period and then level the schedule. Good luck!