S-Curve Shape

8 replies [Last post]
Ali Hamouda
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Hello,

what are the percenages to keep an Curve to S-Shape(S-curve)along a definite period of a project(say 12 months for example)?

Is there an automatic way to divide the values so as to keep an S-curve shape?

What is the technical meaning of keeping the values(example the project cost) to be distributed on S-Curve?

regards for all
Ali Hamouda
=====================================================

Replies

Ali Hamouda
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Hi,

thank you for your time.

If it is possible to see example of this calculations in excel sheet,would be appreciated.

my email: ahamouda@hotmail.com

Ali Hamouda
==========================================
magdy girgis
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 10 May 2004
Posts: 6
Groups: None
ali how are i expexting mail from you
Luca Basile
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
As mentioned by Alex, divide Your work in smallest work packages, for each work packge go more in detail up to your control level (is an engineering or construction project or better and EPC).
Load all the activities with man-hours, costs, then use toold graphic function of P3 and make the hystogram of the costs (bar and cumulative) You will have your S-curve, based on cost, good also for further EVA analysis.
If You want to make it in excel use instead tool report, generate the report in csv, so you can easly make the chart.
What You were telling us about percentage at certain time of the project, You can put some milestone in Your project at their achievement. So if You are sure of the logic, see the group of works that is giving your required percentage and then put a milestone at their end, so You can also easily monitor if You will be in delay or ahead.
Alex Wong
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Amazing how you came up with your s-curve

IMHO the reason why the S-Curve is S shape is due to the nature of the work breakdown sturture (WBS) if you only have one activity per project yes you can use the resource distribution curve to drive your s-curve shape. However, as a planner you have to divid your works into a smaller manageable size of activities and load them with the corresponding % of work load then schedule them into the right time and logic. And that is how you obtain your resource curve. It may vary from project to project but it is a lot accurate than one activity with a res dist. curve.

Forum Guest
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
This is the wrong way to do it
Forum Guest
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
For the purpose of Planned Values.

we have to maintain a certain percenatges when we start to cost load the project

at the first 3 monthes we have to get 12.5% and the 2nd quarter we will get 50% at the following quarter we will get 75% at the end we will get 100 %..

this percenages will lead to a bill or like S-shape curve.

any comment will be appreciated

thanks
Ali
#########################################
Forum Guest
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
If you consider that a curve is generated by cost(or quantity) values from each individual activity, being distributed between the Early (or Late) dates of an activity, then the "shape" of the curve is dictated by the distribution of such cost(or quantity) values, whatever shape that takes. And enforcing a standard "shape" is, IMHO wholly incorrect.
MK TSE
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Consider a bell shape distribution to each item which can be distributed throughout the project.