If you intend to keep the reported stable. I would recommend you create new activities to indicate recovery tasks and load those additional hours to these activities. While calculating progress you can exclude these activities from progress calculation. However, for your manpower calculation (or Histograms) always use complete manhours. This way you know required the manpower as well keep the reported progress consistent.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Wed, 2022-09-07 16:43
if you dont add the additional manhours you will not know how many men you need and can therefore not staff it accordingly
there are 3 ways to recover lost time
option 1 - Crash the Schedule
look at the critical path and reduce durations this will require more manpower to do the same amounto f work in a shorther period of time. Caution check all successor LAGS because if there was a lag especially a start to start lag which was to overlap the successor activity may no longer over lap due to shorting of the duration.
I.E. originaly Activity A 10 days duration successor to activity B Start to start with a 5 day overlap
recovery schedule reduced duration of activity A to 5 days but the relationship stayed the same there for the activites do not overlap as originally indended.
Option 2 - Fast Track the schedule
look at the critical path and make activites there that were to be perfomed sequentially and make them parallel so that they are now scheduled to be doen concurently. Manhours stay the same just logic changes
If the contractor recovery action is to accelerate the program by adding more resources to mitigate the delay without any additional cost to the client, the client might accept the program and accept as a re-baseline or new baseline. This is should be clearly explain in Basis of Schedule.
Member for
16 years 3 monthsAlex IMO- Reduce assigned
Alex
IMO
Member for
14 years 2 monthsZoltan,>there are 3 ways to
Zoltan,
>there are 3 ways to recover lost time.
Sometimes projects need 'Anti-crashing' method:
Anti-crashing is a project management method used to compress a schedule by reducing resources without changing the project’s scope. This includes:
Regards,
Alex Lyaschenko
https://www.linkedin.com/in/alex-lyaschenko-6b630314/
https://saluteenterprises.com.au/blog/
Member for
17 years 8 monthsIf you intend to keep the
If you intend to keep the reported stable. I would recommend you create new activities to indicate recovery tasks and load those additional hours to these activities. While calculating progress you can exclude these activities from progress calculation. However, for your manpower calculation (or Histograms) always use complete manhours. This way you know required the manpower as well keep the reported progress consistent.
Member for
16 years 3 monthsif you dont add the
if you dont add the additional manhours you will not know how many men you need and can therefore not staff it accordingly
there are 3 ways to recover lost time
option 1 - Crash the Schedule
look at the critical path and reduce durations this will require more manpower to do the same amounto f work in a shorther period of time. Caution check all successor LAGS because if there was a lag especially a start to start lag which was to overlap the successor activity may no longer over lap due to shorting of the duration.
I.E. originaly Activity A 10 days duration successor to activity B Start to start with a 5 day overlap
recovery schedule reduced duration of activity A to 5 days but the relationship stayed the same there for the activites do not overlap as originally indended.
Option 2 - Fast Track the schedule
look at the critical path and make activites there that were to be perfomed sequentially and make them parallel so that they are now scheduled to be doen concurently. Manhours stay the same just logic changes
Option #3 - Crash and Fast Track
implement both options #1 and #2
Member for
17 years 4 monthsthanks rodel..
thanks rodel..
Member for
19 yearsIf the contractor recovery
If the contractor recovery action is to accelerate the program by adding more resources to mitigate the delay without any additional cost to the client, the client might accept the program and accept as a re-baseline or new baseline. This is should be clearly explain in Basis of Schedule.