go to resource usage profile or resource usage spreadsheet in the right area right click
if using spreasheet profile select spreadsheet optioncheck calculate average and check base on hour per time period
if using resource useage profile right click on the right area and select Resource usage profile options
then click on the graph tab
at the bottom check calculate Average and check Base on Hours per time period
what this does is it automatically adjusts the resource distrubition based on the time scale that you choos be it days, week or months.
another note is that if you have any resources assigned to an activity type as a LOE (level of effort) you must assign a resource curve to that resource for the LOE activity. If you do nto do this then all of the resources for this activity will be show on the data date.
Member for
16 years 3 monthsgo to view show on bottom go
go to view show on bottom
go to resource usage profile or resource usage spreadsheet in the right area right click
if using spreasheet profile select spreadsheet optioncheck calculate average and check base on hour per time period
if using resource useage profile right click on the right area and select Resource usage profile options
then click on the graph tab
at the bottom check calculate Average and check Base on Hours per time period
what this does is it automatically adjusts the resource distrubition based on the time scale that you choos be it days, week or months.
another note is that if you have any resources assigned to an activity type as a LOE (level of effort) you must assign a resource curve to that resource for the LOE activity. If you do nto do this then all of the resources for this activity will be show on the data date.