Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Resource Usage Profile Budget

5 replies [Last post]
Samir Aliyev
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 15 Sep 2017
Posts: 7
Groups: None

Hi Everybody,

Could you please help me.

In Resource Usage Profile first pictures my budget (yellow colour) shown on 28 October 2017, but it actual( blue colour) started on 01 March 2017. I think it should be the budget and actual stand near each other(like Picture 2). Am I right?

5436
capture.png

 

 

5438
capture1.png

Replies

Samir Aliyev
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 15 Sep 2017
Posts: 7
Groups: None

Hi Everybody,

Could you please help me.

In Resource Usage Profile first pictures my budget (yellow colour) shown on 28 October 2017, but it actual( blue colour) started on 01 March 2017. I think it should be the budget and actual stand near each other(like Picture 2). Am I right?

5442
capture.png

 

 

5441
capture1.png

Samir Aliyev
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 15 Sep 2017
Posts: 7
Groups: None

Hi Everybody,

 

When I assigned baseline project to current I have problem with shedule % complete and activity % complete, wrong calculate schedule (planned) % complete. I think the both % should be the equal. Baseline date and current date the same, different only between two % complete. Could somebody please help me?

Regards,

 

Samir

    

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Samir Aliyev
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 15 Sep 2017
Posts: 7
Groups: None

Thanks fo help.

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes becasue August 26 is a Saturday and I bet your setting are to start the week in Sunday. That is why you have actuals and forecasted units for the week of Ausgust 20 th. The actuals are from August 20th to August 25 and the remaing units are for August 26th. Go to Admin Preferences and go to the General tab change the Starting Day of the week to Saturday or just change your data date to August 27th