Planning, Scheduling & Programming Discussion Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Wed, 2016-02-10 16:51 Permalink Hi Jordan,I'll keep updating Hi Jordan, I'll keep updating the schedule to reflect actuals but without assigning a % complete until the schedule is submitted to the client for approval. In other words, all activities will appear as Planned Dates but those between Project Start Date and Time Now will reflect reality. =jerome http://plannerstips.blogspot.co.uk/ Log in or register to post comments
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Wed, 2016-02-10 16:51 Permalink Hi Jordan,I'll keep updating Hi Jordan, I'll keep updating the schedule to reflect actuals but without assigning a % complete until the schedule is submitted to the client for approval. In other words, all activities will appear as Planned Dates but those between Project Start Date and Time Now will reflect reality. =jerome http://plannerstips.blogspot.co.uk/
Member for
21 years 9 monthsHi Jordan,I'll keep updating
Hi Jordan,
I'll keep updating the schedule to reflect actuals but without assigning a % complete until the schedule is submitted to the client for approval.
In other words, all activities will appear as Planned Dates but those between Project Start Date and Time Now will reflect reality.
=jerome