Progressing a Schedule Before Baselining

Member for

21 years 9 months

Hi Jordan,

I'll keep updating the schedule to reflect actuals but without assigning a % complete until the schedule is submitted to the client for approval.

In other words, all activities will appear as Planned Dates but those between Project Start Date and Time Now will reflect reality.

  =jerome

http://plannerstips.blogspot.co.uk/