These are few things in your post that jump out at me.
First you say that "I have assigned it a baseline and started updating weekly". yet you say "The data date is same as before and I checked the calendar as well".
If you are updating this weekly then the data date should change each week to reflect the date thru which progress is for that particular week.
Secondly you say that "Two weeks later,I had to add an activity to the baseline microprogram.I imported it back and when I scheduled it,it shows a negative total float of -6!!"
Why would you add a new activity into the baseline and not teh current schedule.
Also you added an activity this could be on the critical path causing the negative float of -6.
.
Member for
21 years 7 months
Member for21 years8 months
Submitted by Rafael Davila on Sat, 2015-11-21 18:16
Check for out-of-sequence progress after making sure there are no external links, no activity date constraints, no project level finish constraint.
Depending on your settings out-of-sequence can be identified by the activity being split with progress before DD and remaining duration some time after DD.
Member for
16 years 3 monthsThese are few things in your
These are few things in your post that jump out at me.
First you say that "I have assigned it a baseline and started updating weekly". yet you say "The data date is same as before and I checked the calendar as well".
If you are updating this weekly then the data date should change each week to reflect the date thru which progress is for that particular week.
Secondly you say that "Two weeks later,I had to add an activity to the baseline microprogram.I imported it back and when I scheduled it,it shows a negative total float of -6!!"
Why would you add a new activity into the baseline and not teh current schedule.
Also you added an activity this could be on the critical path causing the negative float of -6.
.
Member for
21 years 7 monthsCheck for out-of-sequence
Check for out-of-sequence progress after making sure there are no external links, no activity date constraints, no project level finish constraint.
Depending on your settings out-of-sequence can be identified by the activity being split with progress before DD and remaining duration some time after DD.
Good Luck